Close

Login

Please login with your username and password.

Login

Can’t remember your accounts password?

Can't access your account?

Please select your language

This page is available in the following languages:

    Please select your location

    ​​​​​Project Reference: MasterFlow - ​Liquefied natural gas (LNG) Shore Trunkline Microtunnel


     Source: Chevron

    ​Location: Wheatsone Project, Onslow, Western Australia
    Applicator/Contractor: Subcon Technologies Pty Ltd, Dredging International Australia
    Market sector: Energy
    Products used: MasterFlow 700​ cementitious, non-shrink construction grout which undergoes controlled expansion in the plastic state 

    Download the Project Reference PDF​

    The Background

    Chevron’s Wheatstone Project is a multi-train Liquefied Natural Gas (LNG) and domestic gas plant located on the Pilbara Coast, Western Australia. The Wheatstone Project involves processing gas from various fields located offshore and ​the installation of gas gathering, export and processing facilities in water and on land. The gas is transported to the Wheatstone LNG plant from subsea wells through a trunkline, several kilometers offshore. The last kilometer of the trunkline is sent in from the shoreline through a protective mi​​crotunnelThis project was located in an environmentally sensitive area, in close proximity to a whale shark breeding ground, which proved a challenge. 

    The Challenge​​

    During tide changes, a grout plug is required ​inside the tunnel annulus extending 70 meters inside the microtunnel to block water flow. The challenge was to anchor the last 70 meters of the trunkline within the microtunnel to shore with a precision grout plug. Since placement of the grout had to be done underwater with low visibility, the team had to develop a new design concept for grout movement, placement and mixing. Considering the close proximity of the project to the shark breeding ground, environmental factors had to be taken into consideration to ensure zero environmental impact. ​

    Our Solution

    A new grout delivery system was designed to overcome some of the challenges. This included a unique trolley system which carried the delivery line and inflatable grout bags down the 70 meter microtunnel underwater. The grout and water temperature was reduced to 4 degrees Celsius for 48 hours before use, using several refrigerated containers. The design of the delivery trolley also assisted temperature control by enabling rapid product placement. Best practices were employed for working in environmentally sensitive areas that had zero tolerance for any spills. ​

    Project Facts at a Glance

    • ​The project was in the design phase for almost two years, the actual placement of the grout was completed in 36 hours.
    • ​Two mock-up trials were also conducted before the final application of the grout.
    • ​The project now boasts the first-ever microtunnel plug installed worldwide. 

    Product Facts at a Glance

    • ​​MasterFlow 700​ is a Class A grout generally used in applications requiring a grout thickness between 10mm and 100mm
    • It is a ready-to-use premixed grout that only requires the addition of mixing water on site
    • It is economical due to its ease of use and flowable properties
    • It has a low water/cement ratio therefore reducing drying shrinkage and increasing durability


    The Customer's Benefit

    • A difficult project was delivered on time and within budget.
    • ​The on-site costs to the customer were reduced due to the speed of the pour (36 hours non-stop).
    • ​The grout plug provided the trunkline with an anchor that was impermeable to tides and intermittent water and air ingress, improving the durability and life cycle of the structure.
    • ​The solution reduced the possibility of future corrosion costs.


     The Wheatstone Project is located in close proximity to an important whale shark breeding ground, meaning various environmental factors needed to be considered when developing Master Builders Solutions' grout delivery system. ​

    Direct contact

    Andrew Sarkady

    Andrew Sarkady

    National Industry Advocate Civil Infrastructure – Transport

    0418 530 763