    Cadia East Mine

    Cadia East Mine

    When setting roadway panels in underground construction, there can often be too much shrinkage with the grout. MasterRoc MG100, a non-shrink grout additive was used to provide flow and stability in the project at hand, whilst also reducing shrinkage.

    Castle Hill Holden

    Castle Hill Holden

    In large car dealerships, the workshop is essentially a ‘second showroom’.  To maximise quality, safety and aesthetics, Prime Constructions specified MasterTop® 1080 for the workshop floors and walls.

    City Reach Boardwalk Brisbane River

    City Reach Boardwalk Brisbane River

    O’Connor Kelly and Master Builders Solutions completed a refurbishment project at the City Reach Boardwalk utilising various MasterEmaco and MasterProtect products for both corrosion repairs and structural repairs.

    Darlot Gold Mine

    Darlot Gold Mine

    MasterRoc MF 505C used to increase the quality of paste fill, in order that paste development, side exposure and undercut curing times could be ​reduced and Lode 1 extraction rate increased.

    Fonterra Milk Processing Plant

    Fonterra Milk Processing Plant

    Milk processing plant Fonterra required a Ucrete DP flooring system that was able to withstand heavy traffic (foot and equipment), strict hygiene/cleaning standards, resistance to harsh chemicals and temperatures, and a safe slip-resistant surface.

    Gorgon liquified gas (LNG) project

    Gorgon liquified gas (LNG) project

    The Gorgon Project is one of the world's largest natural gas projects and the largest single resource development in Australia's history. In order to build the facility, Gorgon needed a supplier that could deliver the full range of precision grouting products, which is where Master Builders Solutions stepped in. The MasterFlow range was used during construction, with a range of environmental and regulatory challenges being considered.

    Legacy Way Tunnel

    Legacy Way Tunnel

    Construction of Brisbane City Council’s Legacy Way Tunnel in Brisbane’s inner city was undertaken by the Transcity Joint Venture. Small cross passages that connect up with Tunnel Boring Machines were constructed for evacuation and emergency services and the shotcrete required for the tunnel lining had to be delivered to meet TJV’s continuous operation program.

    Lion Nathan East Tamaki Brewery

    Lion Nathan East Tamaki Brewery

    The new brewery was commonly referred to as Project Century - in reference to the facility’s projected life-span of 100 years. The facility was developed with a focus on quality, long-term performance and reduced environmental impact. Ucrete DP by Master Builders Solutions was chosen due to its versatile and hard-wearing nature.

    Liquefied natural gas (LNG)

    Liquefied natural gas (LNG)

    The Wheatstone Project involves processing gas from various fields located offshore and ​the installation of gas gathering, export and processing facilities in water and on land. The MasterFlow grout delivery system was able to provide solutions to some problems relating to the Shore Trunkline Microtunnel.

    MB Solutions Australia Pty Ltd Seven Hills site

    MB Solutions Australia Pty Ltd Seven Hills site

    At the MB Solutions Warehouse in Sydney, a driveway was affected and needed repair. A joint between two slabs (one sloping) had opened up over time and had become contaminated with dirt and debris, as well as the exposed edges showing signs of damage. The MasterSeal CR 435 joint sealant proved perfect for the task at hand, considering the driveway needed to be resealed during working hours without disrupting activities on site.

    MasterLife 300D

    MasterLife 300D

    Shotcrete is widely used in Hard Rock mines for ground support, allowing the customer a safe and efficient mining operation. In damp and wet areas, shotcrete may be difficult to apply where fall out can occur due to the shotcrete not bonding to the wet substrate. Master Builders Solutions proposed the addition of MasterLife 300D, a crystalline capillary waterproofing admixture, to the shotcrete mix in conjunction with MasterLife SF100, a dry powdered silica fume.

    McCains Smithton Vegetable Processing Plant

    McCains Smithton Vegetable Processing Plant

    After a series of trials, Master Builders Solutions Ucrete DP flooring was chosen to be installed at the McCains Vegetable Processing Plant in Smithton, Tasmania. In the past, McCain Foods had found that many of their floor toppings were not able to withstand the harsh operating environment and were being damaged by acids, oils and machinery. Ucrete DP was chosen due to its effective and long-lasting capabilities